Sample questions with answers

A few questions of the kind you will get in this test. Try them, then open the answer.

  1. 🏗️ Civil Engineering

    Q1. Plastering is measured in —

    • A.Quintals
    • B.Cubic metres (m³)
    • C.Square metres (m²)
    • D.Running metres (m)
    Show answer & explanation

    Answer: C. Square metres (m²)

    Plastering, painting and flooring are surface works, so they are measured by area in m². 🧠 Volume (m³): earthwork, concrete, brickwork; area (m²): plaster, paint, flooring; weight: steel.

  2. 🏗️ Civil Engineering

    Q2. As per IS 1200, no deduction is made in brickwork for openings of area up to —

    • A.1.0 m²
    • B.0.5 m²
    • C.0.1 m²
    • D.2.0 m²
    Show answer & explanation

    Answer: C. 0.1 m²

    Small openings up to 0.1 m² are not deducted from brickwork; larger openings are deducted. 🧠 Extra labour around small openings balances the material saved.

  3. 🏗️ Civil Engineering

    Q3. The provision for contingencies in an estimate is usually —

    • A.20% of the estimated cost
    • B.Less than 1% of the estimated cost
    • C.3% to 5% of the estimated cost
    • D.10% to 15% of the estimated cost
    Show answer & explanation

    Answer: C. 3% to 5% of the estimated cost

    About 3–5% of the estimated cost is added for contingencies: small unforeseen items of work. 🧠 Work-charged establishment is a separate provision of about 1.5–2%.

  4. 🏗️ Civil Engineering

    Q4. A sinking fund is created to —

    • A.Meet the cost of daily repairs
    • B.Pay the property tax
    • C.Replace a building or asset at the end of its useful life
    • D.Pay the monthly salaries of staff
    Show answer & explanation

    Answer: C. Replace a building or asset at the end of its useful life

    A sinking fund is a fixed amount set aside every year so that enough money is available to replace the asset when its life is over. 🧠 It is part of valuation; it is linked to depreciation of the building.

  5. 🏗️ Civil Engineering

    Q5. Approximately how many bags of cement are needed for 1 m³ of 1:2:4 concrete?

    • A.About 10.4 bags
    • B.About 8.4 bags
    • C.About 4.4 bags
    • D.About 6.4 bags
    Show answer & explanation

    Answer: D. About 6.4 bags

    Dry volume ≈ 1.54 m³. Cement = 1.54 × 1/7 = 0.22 m³. One bag = 0.0347 m³, so 0.22 ÷ 0.0347 ≈ 6.3–6.4 bags. 🧠 Dry volume factor 1.52–1.57 for concrete; one 50 kg bag = 0.0347 m³.

How the test works

  • Click Start the test, enter your name if you like, and the timer starts. No login is needed.
  • Switch between Hindi and English at any time with the EN / हिं button.
  • Each correct answer gives +4 marks and each wrong answer −1, like the real exam. Skipped questions give 0.
  • At the end you get your score, accuracy, estimated percentile, subject-wise performance and an explanation for every question.
  • Download a free PDF report to revise later.
Start SSC JE Civil – Estimating & Costing →

More free tests

See all tests →